Machine relocation checklist: 12 steps to move a production machine

Most problems in a machine move are not caused by the lift or the truck. They come from a missing drawing, a foundation that is not ready, or a power supply nobody checked. This checklist follows the order in which a relocation actually runs – use it to plan your own move or to check an offer.

Machine relocation checklist: 12 steps to move a production machine

Before anything is disconnected

Start with a site survey at both locations. The team that will do the work should see the machine, the access route, door and hall heights, floor load capacity and the crane or rigging options on site. A relocation planned from photos alone usually ends in surprises on the day of the move.

  • 1. Survey of the old and the new site, including access routes and floor loads
  • 2. Collect the documentation: layout drawings, foundation plans, electrical and hydraulic diagrams, manufacturer manuals
  • 3. Record the current condition – photos, videos, measured geometry and a test run with a record of cycle times and quality
  • 4. Decide what moves as one piece and what has to be dismantled, based on weights, dimensions and transport limits

Preparing the new location

The new site has to be ready before the machine arrives, not afterwards. Heavy machines often need their own foundation, and concrete needs time to cure before it can take the load. Utilities – power, compressed air, cooling water, extraction – should be in place and tested.

  • 5. Foundations and anchor points according to the manufacturer’s drawings
  • 6. Utilities at the new position: power supply, compressed air, cooling, extraction, network
  • 7. A clear schedule of who does what: rigging team, electricians, the machine manufacturer, your maintenance team
Service

Need a team for your relocation?

Our partner team handles the whole sequence – from the survey to commissioning – with one coordinator and lifting capacity up to 1,100 t.

Machine relocation across Europe →

Moving day

Dismantling is where documentation pays off. Every cable and every part should be match-marked before it is removed, so the machine can be rebuilt without guesswork. The lifting method depends on the weight and the space available: hydraulic gantry systems, skates and jacks work where a crane cannot reach.

  • 8. Disconnection, draining of oils and coolants, securing of moving parts
  • 9. Match-marking and dismantling into transportable units
  • 10. Rigging, loading and transport with load securing suited to each component

Installation and restart

At the new location the order is reversed: positioning, levelling, anchoring, reconnecting utilities and finally commissioning. The machine is only “moved” when it produces parts at the agreed quality again – compare the result with the test run you recorded before the move.

  • 11. Positioning, levelling and alignment, reassembly and reconnection
  • 12. Commissioning, test run and handover with a protocol

FAQ

Frequently asked questions

How long does it take to relocate a production machine?

It depends on the size of the machine, the amount of dismantling and the readiness of the new site. A single machine can be moved within days; a large press or a line needs a detailed schedule. The preparation – survey, documentation and foundations – often takes longer than the move itself.

Do we need the machine manufacturer for the relocation?

Not always. An experienced rigging and installation team can dismantle, move and reinstall most machines. For control systems, warranty questions or very complex machines it makes sense to involve the manufacturer for commissioning.

What is the most common mistake in machine relocation?

Starting too late with the new site. Foundations, utilities and access have to be ready when the machine arrives – otherwise the team waits and downtime grows.

Tell us about your project

Send us the machine type, weight, current and new location and your timeframe. You will receive a proposed method and a budget estimate.

Thank you – your enquiry has been sent.

We will get back to you within one business day.

Scroll to Top
Request a quote →